Introduction of the production cycle of fruit buttons

Production cycle

Proofing:

Ordinary single buckle——————5 days

Ordinary laser buckle——————5 days

Shaped buckle————————6 days

Dyeing Deduction Laser ————— 7-8 days

Big goods:

Ordinary single buckle——————8 days

Ordinary laser buckle——————9 days

Shaped buckle————————9-10 days

Dyeing Lasers——————10-11 days General production cycle is 7-9 days

The specific distribution of each process:

1, scheduling and size development ------- 0.5-1 days

2, deduction, laser ----------- 1-2 days

3, polishing (water rolling) ---------- 1 day (usually at night, the next morning and next time)

4, staining --------------- 3-5 days

5, polishing roll, inspection, packaging ---- 1-2 days

Note: Dyeing time depends on the degree of color difficulty and batch size (engraved finished buckle or antique, scrub, etc. need to increase the appropriate extension of the process) (1) Black will be 1-2 days in advance.

(2) Delay of 2 days for hot and matte, and 3-4 days for antique.





Want to learn more about buttons: accessible

For more details, please pay attention to WeChat public number:


ACRYLIC NYLON CORE SPUN YARN

Acrylic Nylon Core Spun Yarn,Acrylic Core Spun Yarn,Acrylic Nylon Blended Yarn,Pbt Core Spun Yarn

ZHANGJIAGANG WELLHOW TRADING CO., LTD. , https://www.wellhowyarn.com

Posted on